Project time: December 2020Project location: Dongying, Shandong Project composition: 40mwp photovolt

Description

Project time: December 2020

Project location: Dongying, Shandong 

Project composition: 40mwp photovoltaic grid connected power station project energy storage supporting 8mw/16mwh

Project significance: the project is a joint operation of photovoltaic and energy storage on the power generation side. It can not only use local resource endowments to respond to power grid peak and FM auxiliary services, alleviate power shortage during peak periods, but also use photovoltaic + energy storage mode to form an advanced demonstration effect.